Exterior wall cleaning and maintenance construction programme
Project profile and basis for preparation
Project overview
Project name: cleaning and repair of the outer wall of the xxxx building
Project location: xx road xx, xx city
Project size: the total height of the building is xx floors, the total area of the building is xx square metres and the outer wall is xx square metres。
Structure: framework structure
Use function: office, commercial, residential
Construction standards: compliance with national quality standards for construction works
Design overview: the exterior wall cleaning and maintenance works include, inter alia, exterior glass cleaning, exterior wall maintenance and exterior wall coating repairs。
Main features and difficulties:
(1) the building is located in the centre of the city and the surrounding area is busy, and traffic safety is required during construction work
(2) high floors of buildings, with high operational safety to be considered during construction
(3) there are varying degrees of stains and damage to the exterior glass and the walls, which require targeted cleaning and repair
(4) the outer wall coatings are detaching and require repair and re-painting。
Basis for preparation
(1) relevant laws and regulations: building law of the people's republic of china, safety of production law of the people's republic of china, uniform standards for the quality of construction works, etc.
(ii) standard norms: technical specifications for high-altitude operating safety, acceptance standards for quality of construction work, etc.

(3) design drawings: the project design drawings and related technical documents
(4) construction design: construction design documents for the project
(5) engineering contract: the contract for the project and the related agreement。
Construction design
1. Project management body
In order to ensure the smooth running of the project, a dedicated management team was established, with the following structure and division of responsibilities:
(1) project manager: responsible for the overall construction, coordination and management of the project and for the overall control of project progress, quality and safety
(ii) technical officer: responsible for the development of technical programmes for construction, technology flooring and technical guidance during construction
(3) construction staff: responsible for the day-to-day management of the construction site, including construction schedule, quality, security, etc.
(4) quality detector: responsible for quality testing and acceptance during construction
(5) security officer: responsible for the security management of the construction site and ensuring the safety of personnel during the construction process
(6) material clerk: responsible for material supply and inventory management
(7) equipment manager: responsible for the management and maintenance of construction machinery and equipment。
2. Construction workforce configuration
Based on the construction characteristics and difficulties of the project, the total number of construction teams is xx, with the following professional composition and required skills:
(1) high-altitude operators: xx with high-altitude operating certificates and familiar with high-altitude operating safety protocols
(2) purge maintenance staff: xx personnel with relevant construction skills and familiar with external wall cleaning and repair processes
(3) painter: xx with the skills to coat and build and familiar with the coating restoration process
(4) security guardians: xx persons with security custody certificates and familiar with security management at the construction site。
3. Labour, materials, equipment schemes

(1) workforce use plan: rationalize the work schedule of the construction staff in accordance with the construction schedule and workload to ensure adequate labour capacity during the construction process
(2) material supply plan: preparation of an advance material supply plan to ensure the timely delivery of materials in accordance with the construction drawings and construction programme
(3) plan for the use of construction machinery: rational arrangements for the use of construction machinery in accordance with construction requirements to ensure the smooth running of construction。
This section provides a detailed description of the construction design, including the project management structure, the construction workforce configuration and the workforce, materials and equipment plan. The content is in line with the actual conditions of construction and ensures that the skills, management, construction skills and resource allocation in the construction process are adequately safeguarded。
Iii. Construction methods and technical measures
Construction methodology
(1) exterior glazing: the use of specialized cleaning equipment, such as robots, guns etc., in conjunction with cleaning agents. During the cleaning process, the glass surface is examined in detail and the stains are cleaned in a targeted manner. After the clean-up is completed, it is washed with water to ensure that the glass surface is clean and transparent。
(2) maintenance of the exterior wall: refurbishment of the wall with appropriate maintenance materials, including stains, damage, etc. When the surface of the wall is removed, the damage is removed, then polished, patched, and the corresponding coating is finally painted。
(3) refurbishment of the exterior wall coating: refurbishment of the decorated and damaged areas, first to remove the decorated parts, then to grind, then to paint, and finally to paint. In the coating restoration process, attention is paid to parameters such as the uniformity of the coating, saturation and the temperature of construction。
2. Technical measures
(1) high-altitude operational safety: the construction of safety shields and the wearing of protective equipment such as seat belts, helmets, etc. By the construction personnel. High-altitude operational equipment is regularly inspected and maintained to ensure its safety and reliability。
(2) construction quality control: construction is carried out in strict compliance with the construction drawings and the construction programme to ensure the quality of construction. Quality testing of critical elements of the construction process, such as paint varieties, coating thickness, etc。
(3) construction protection of the environment: during the construction process, effective measures are taken to reduce the impact on the surrounding environment, such as containment, dusting, etc. The waste generated from construction is properly treated to avoid contamination of the environment。
(4) seasonal construction measures: the implementation of appropriate measures to ensure the smooth running of the work in response to climatic conditions in different seasons. For example, construction time is rationalized to avoid high-temperature periods during high summer temperatures, and materials and equipment suitable for low-temperature construction are selected during winter temperatures。
This section details construction methods and technical measures, including outside wall glass cleaning, exterior wall maintenance and outer wall coating repairs, as well as technical measures such as high-altitude operational safety, construction quality control, construction environmental protection and seasonal construction measures. Ensuring adequate safety, quality and environmental protection during construction。
Iv. Payment of the place of the station
1. General floor layout of the construction site
(1) temporary facilities: temporary facilities such as construction site offices, lounges and temporary toilets to ensure that the living needs of the construction staff are met

(2) roads: planning of internal roads at the construction site to ensure smooth movement of construction vehicles and personnel
(3) material dumps: rational planning of material stacking areas to ensure that materials are classified, stacked, easily managed and used
(4) processing sites: appropriate processing sites, such as paint transfer areas, maintenance operating areas, etc., according to construction needs
(5) safety and protection areas: to ensure the safety of the construction site by setting up safety and protection areas, including security warning signs, guard posts, etc。
2. Phased floor layout
In accordance with the schedule of construction, a phased adjustment and optimization of the floor layout of the construction site will be undertaken to ensure the smooth running of construction. For example, during the glass cleaning phase, emphasis is placed on cleaning equipment, material storage areas; during the wall repair phase, emphasis is placed on maintenance operating areas, material storage areas; during the coating restoration phase, emphasis is placed on coating redeployment areas, coating construction areas, etc。
This component provides, inter alia, detailed planning of the floor layout at the construction site, including the overall floor layout at the construction site and the phased floor layout. The content is in line with the actual construction conditions and ensures order, security and efficiency at the construction site。
V. Progress plan and pursuant measures
Construction schedule
The construction schedule for this project is set at xx days and the construction schedule is as follows:
(1) clearing of external wall glass: days 1-7, completion of all glass cleaning
(2) maintenance of the outer wall: day 8-15, completion of all wall maintenance
(3) exterior wall coating repairs: 16-20 days, completion of all coating repairs。
Key nodes:
(1) day 3, completion of commissioning and preparation of glass cleaning equipment
(2) day 10, completion of procurement and acceptance of wall maintenance materials
(3) day 15, completion of allocation and trial painting of coating restoration material。
2.