A 33-storey house from the base pit to the delivery process

2026-06-29 00:181710NameNetworking

Map of the construction of a flower shelf plant

This is an example of the entire process through which a 33-storey house was dug from the base pit to its completion:

1. Land purchase

Before looking at a piece of land and preparing to start purchasing it, the developer will require the designer to make a preliminary design of the land, calculate the economic technical indicators and estimate the bid price。

Ii. Equipment for construction programme — preliminary designment of constructors — programmatic duration

3. Construction plan design

The civil works builder requested reasonable advice on the design of the construction plans, primarily to ensure that the works could be carried out。

Map of the construction of a flower shelf plant

4. Project management planning paper preparation

Identification of key time nodes, economic benefits, etc., with the ministry of works leading the rest of the real estate company

5. Total contracted entry for construction

Six, three, one, two and a half

7 entry of earth units: ground leveling — basic pit digging

The drawings were obtained, control points were located, building locations were located, before digging should be preceded by precipitation, and the groundwater could not begin until the ground pits below the base mark of 2 m were dug。

Map of the construction of a flower shelf plant

8. Basic pit support works

Map of the construction of a flower shelf plant

9. Anti-floating anchor poles and base construction

The base construction was due to the fact that the test tank was a test of the holding layer structure after the examination of the tank, which ensured that there would be no uneven deposition. The base is mainly for water protection。

Map of the construction of a flower shelf plant

10. Waterproof construction

Underground use of sbs waterproof rolls, followed by waterproof layers. Waterproofing materials are the type, price and range of civil engineers, and waterproofing is key。

Map of the construction of a flower shelf plant

11: base steel binding

The basis is the basis of the raft, the basis of independence, etc. The construction process is different。

Map of the construction of a flower shelf plant

12. Basic construction

Quality check-ups are followed by the installation of basic steel bars。

Map of the construction of a flower shelf plant

13, basements against earth walls

The stinging of the wall is more demanding and should be checked for waterproof concrete。

Map of the construction of a flower shelf plant

14 - top of the basement

Attention is paid to security issues such as the layout of the floors and the ceiling of the basements。

Map of the construction of a flower shelf plant

Project opening

The property project is generally ready for sale at the top of the basement, an important time point。

16, one layer of beam-stretched steel ligation — level-stamping

And then we start the cycle. It's nothing special. Watch the process。

Map of the construction of a flower shelf plant

Map of the construction of a flower shelf plant

17. After the main project has been capped, construction of the body works, the roof of the house and the roof of the basement can commence at the same time. (it's important that the construction elevator be installed at this time; precipitation can stop)

Map of the construction of a flower shelf plant

18. Commencement of the contents project

19. Construction of the contents of the two-module (i. E. Construction of the construction column)

20. Internal wall dusting (building processes and material control are important)

Map of the construction of a flower shelf plant

21 exterior wall dust

The interior wall must be completed before the outer wall is made to facilitate the handling of interface positions。

22, construction of bricks on the outer wall

Sampling, verticality, flatness, etc. Are important and should be done before the outer shelf is removed。

23, land construction

Map of the construction of a flower shelf plant

Waterproof latrine construction

Map of the construction of a flower shelf plant

25. Construction of bricks on the outer wall

Map of the construction of a flower shelf plant

26, synchronizing construction of grc lines in public areas

27. Fireworks and public fittings are completed for installation and public decoration

28, fire-fighting, etc

29, garden hard-walled

Map of the construction of a flower shelf plant

30, joe, bush, greening completed

31. Fire-fighting connection experiment (very important, end of marking work)

Official electricity, water, grid, gas entry

Map of the construction of a flower shelf plant

Overseeing receipt and inspection information, completed acceptance and inspection

Delivery to owners

Like 0
Report
Favorite 0
Tip 0
Comment 0
Share 6
MoreRelated Comments
No comments yet, be the first to comment
Plumbing water: new techniques in mountain medicine cultivation to make the roads rich and rich
Spring doesn't work, autumn doesn't work. At the moment, during the spring planting season, it is also a good time to plant mountain medicine. After several days of tillage, 27 acres of mountain pharmacist farming in the village of sade, the village of lobendra, in the city of shui。Under the guidance of technologists, farmers seize farmers in a spirit of good faith and take every step seriously to map out an early spring crop in the fields

0评论2026-08-11128