Overview of basement and waterproofness
Waterproofing of basements and floors is essential and directly relates to the life and safety of buildings. In the area of construction, waterproofing of basements and floors is essential for building life and safety. This paper will provide details of the method of construction of the basements and the waterproofing rolls on the floor, as well as the handling techniques of the key fine nodes. By reading this paper, you will be able to obtain a fuller picture of the entire process of construction of water-proof scrolls, thus providing strong technical support for actual works。

Two-storey waterproof construction in basement 02
Waterproofing of floors
In the waterproofing work of the two-storey rolls in the basement, additional layers will be required on the floor to ensure waterproofness, such as at the corner. At the corner of the base plate, at the horizontal interface and at the turnover, additional floor rolls should be added to enhance waterproofness。

Construction methods for side walls
During the construction of the side wall, bricks were used for temporary fixation. The use of bricks to temporarily fix the scrolls to ensure the width and softness of the docks and to ensure that the bottom and side wall rolls are at least 150 mm wide。

The method of construction to be carried out with a subsequent draught
In order to enhance the waterproofness of the refills, an enhanced layer is added to the refill position to ensure waterproofness. An additional reinforced layer of the same material as a large volume of scrolls is laid at that location。


Waterproofing of elevator wells and catchment pits
At the turning point of the yang angle of the elevator well and the catchment pit, additional layers are required to ensure waterproofness. An additional reinforced layer of the same material as the large roll。

Exterior wall closing method
The wall's wall's wall's rolls are secured by fixed presses and nails, and are tightly sealed with asphalt-based seals. The outer wall is closed by means of a fixed bar and a sealed ointment to ensure that protection is sustained。

Waterproofing through walls
With regard to waterproofing through walls, we recommend the use of tubes and ensure that their materials are compatible with waterproof materials. Waterproof barriers are constructed using ducts and sealed materials。


Detailed waterproof practices in basements with monolithic rolls
Emphasis was placed on laying details and handling temporary protection walls. In the waterproofing work on the floor, it is essential to have dedicated waterproofing additions at the horizontal interface and turnover。

Side wall handling
In the course of the construction work on the side wall, the floor and the side wall should be attached to the side wall with bricks temporarily fixed to ensure the width of the line. Use of temporary fixed volume intakes such as bricks。

Recipe treatment
In the latter position, additional reinforced layers of the same material as large rolls will be required to enhance water resistance in the region。
Waterproofing of elevator wells and catchment pits
An additional reinforced layer of the same material as the large roll will also be laid to ensure the waterproofness of these critical areas。

Exterior scroll collection method
The side nodes of the outer wall closing method include the application of the high and soft waterproof layer of the portal, thus providing details of the height and soft closing measures。


Waterproofing through walls
Settling and sealing material filling constitute a waterproof barrier. This is achieved through pre-laying tubes and sealing material filling。
Two-storey waterproofs on room 03
Waterproof construction process on two floors
During the waterproofing of the two-storey floors of the house, the order of construction of the house and the detail nodes were processed. First, the house is treated at the grass-roots level to ensure that it is flat, clean and wet。

My daughter's wall is closed
In the waterproof construction of the house, the end-of-the-wall treatment of the daughter's wall is essential. The complete treatment of the daughter's wall's waterproof node and additional layers is usually accompanied by additional layers of the same material as the large rolls。



Method of waterproofing construction of the exterior pipe
The waterproofing parcels are connected to thermal melting to ensure that they are kept secret and that waterproofing effects are ensured through the collage wrapping and thermal melting。

Waterproof construction methods on the surface
Waterproofing of water landings is subject to specific steps, with water landing cups embedded and covered with rolls to ensure the integrity of their waterproof layer。


Waterproof construction methods on one floor of the house
Emphasis is placed on basic treatment and full-scale construction of sub-nodes to ensure waterproofness through a reasonable construction process。


Waterproofing methods for out-of-house pipes
Sealed and waterproofing of out-of-house pipes to ensure no leakage。

Waterproofing across water
The treatment and slope design around the water landing vent to ensure a smooth flow of drainage and prevent leakage through sealed treatment and reasonable slope design。

Straight-waterproofing
The sealing and slope design of the direct water vent reduces the risk of leakage and ensures a smooth drainage of the house。

04 water protection measures for the cultivation of houses
Waterproofing of large surfaces
In the waterproofing work of the house, high-quality materials are selected to ensure that the house is fully waterproof。

Handle the top plate and the wall
The ideal combination of materials ensures seamless docking and prevents water infiltration。

Waterproof construction methods for the upper platform
Waterproofing works on the upper platform include reasonable construction processes and selection of waterproofing materials to ensure safety of use。