Hello, welcome toPeanut Shell Foreign Trade Network B2B Free Information Publishing Platform!
18951535724
  • Air conditioning maintenance programme 73164 - page 1

       2026-07-06 NetworkingName760
    1111111
    Key Point:Air conditioning maintenance programme 73164 - page 1Air-conditioning maintenance programmeProgramme bookApril 2018Air conditioning maintenance programme 73164 - page 1Ac programme 73164 - page 2I. Project overviewProject name: air conditioner maintenanceProject unit: companyEngineering scale: daily fluorinated cleaning and maintenance of 303 air conditioners, two central air conditioner hostsPipelines, etc., 2 repairs and maintenance, central ai

    Air conditioning maintenance programme 73164 - page 1

    Air-conditioning maintenance programme

    Programme book

    April 2018

    Air conditioning maintenance programme 73164 - page 1

    Ac programme 73164 - page 2

    I. Project overview

    Project name: air conditioner maintenance

    Project unit: company

    Engineering scale: daily fluorinated cleaning and maintenance of 303 air conditioners, two central air conditioner hosts

    Pipelines, etc., 2 repairs and maintenance, central air-conditioning mainframe oil replacement, soft water tanks, pumps

    Replacement of electric axle bearings, replacement of indoor air conditioning.

    Transport, transport: road transport

    Ii. General segment

    1 general provisions

    1. 1 this regulatory document proposes technologies for air conditioning maintenance, etc

    Request.

    1. 2 this norm sets minimum requirements and does not provide for all technical details, nor

    The provisions on standards and norms are not fully quoted and the supply side should provide for compliance with these norms and industrial standards

    Quality products.

    1. 3 contractors must be registered in the people's republic of china and qualified for construction work iii

    Independent legal person of an enterprise of grade and above. ... The tenderer shall accompany the tender in providing the required proof of qualification man

    Documentation of shipments . 5.

    Ac programme 73164 - page 2

    Air conditioning maintenance programme 73164 - page 3

    Air-conditioning maintenance technology

    1. 4 if the bidder does not object to the provisions of this norm in writing, it expresses its vote

    The equipment provided by the subject fully meets the requirements of this norms, and where it is inconsistent with the requirements of this norms,

    Each item must be listed in the “project unit technical discrepancy table”

    In the table of technical discrepancies for project units, it is stated that "no difference,o

    1. 5 the criteria used in this instruction are higher if inconsistent with the standards implemented by the bidders

    Commencing.

    1. 6 this instruction will be annexed to the order contract and will have the same legal effect as the contract ..

    Failure to do so is determined by agreement between the parties to the contract during the negotiation of the contract.

    1. 7 supply-side responsibilities: the terms of reference will include, but are not limited to:

    1. 7. 1 provide all equipment and design instructions and manufacturing specifications in the tender.

    1. 7. 2 provision of instructions for installation and use of equipment.

    1. 7. 3 criteria for testing and testing, including test reports and test data ...

    1. 7. 4 provision of drawings, a list of the manufacturing and quality assurance processes and other requirements of the tender

    Information.

    1. 7. 5 provision of relevant information for equipment management and operation.

    1. 7. 6 the equipment provided shall be shipped to the specified destination and shall be responsible for on-site installation and commissioning ...

    Air conditioning maintenance programme 73164 - page 3

    Ac maintenance programme 73164 - page 4

    1. 7. 7 if there is an apparent conflict between standards, norms and the provisions of this norm, the supplier shall manufacture

    Prior to the equipment, the conflict and resolution are communicated in writing and confirmed by the required party only in

    Equipment manufacturing.

    1. 7. 8 supply side when replacing guidelines, standards, protocols or modifying technical data for equipment

    The duty to accept the choice of the demand side.

    General technical requirements

    2. 1 quoting criteria

    All spare parts, assembly components required for the project, including all attachments and accessories obtained by the construction party from third parties

    Air-conditioning maintenance technology

    Equipment, etc., other than the technical parameters and requirements specified in this instruction, shall follow the latest version

    Standard dl for the electricity sector, national standards gb and iec and international system of units (isi)

    Minimum requirements for equipment. The construction party must provide the tenderer with its own standards or specifications

    Photocopies in chinese may only be adopted with consent, but not less than the relevant provisions of dl, gb and iec.

    2. 2 maintenance requirements

    1. The contractor is responsible for the completion of all major repairs.

    2. Spare parts provided by the major repair contractor: see list of works.

    3. The contractor undertakes to complete the construction within one month of the signing of the contract.

    Iii. Equipment, materials

    Material equipment to be provided by bidders:

    Ac maintenance programme 73164 - page 4

    Ac programme 73164 - page 5

    Quota

    Number of engineering project units

    Numbering

    Central air-conditioning mainframe switch

    1kg130

    Two hundred electromagnetic valves four

    3 soft water tank 1

    4 pumps for re-axis water cover 2

    5 water pumps to replace kw15

    6. Replacement of 10 indoor air conditioners

    7 ac plus fluorine pressure 150

    8 air-conditioning cleaning agent kg300

    List of works:

    1. Budget for volume of work as detailed in the list of volume of work.

    Air-conditioning maintenance technology

    2. The unit price or amount stated in the schedule for the volume list shall include the labour requirement, the construction unit

    Fees for the use of ordnance, materials, other miscellaneous charges, quality checks, installation costs, repair of defects, insurance,

    And the risks, liabilities and obligations expressly or implied by the contract, as well as management fees, profits, etc.

    3. The final volume of work is based on the actual quantity of work performed.

    Construction requirements

    1. Technical requirements

    Ac programme 73164 - page 5

    Ac programme 73164 - page 6

    L all equipment materials must be purchased to the specifications and models required by a and to the requirements of a in

    Line installation.

    2 equipment purchased by maintenance units from other plants, with all quality issues to be addressed by the maintenance unit.

    3 maintenance unit to establish quality of equipment design, material selection, processing, manufacturing and testing

    Guarantee system and strict compliance with contract equipment throughout its manufacture ...

    2. Work to be performed by bidders

    1 receipt and custody of equipment and materials required for construction, secondary handling of site equipment and materials, installation

    Loading and testing, system testing and debugging, cleaning of used materials, engineering files and transfer of information

    Completion and warranty.

    2 purchases of equipment for which the bidders are responsible should be carried out in a timely manner in accordance with the schedule and related procurements

    Results are reported in a timely manner to the user unit, the supervisor, so that the user unit can cooperate in a timely manner, such as delays in the delivery of procurement

    The subject should be fully responsible.

    3 provisional facilities for bidders:

    4 bid parties should maintain a high level of responsibility and ownership during construction preparation and construction

    Pay attention to the protection of finished goods in the vicinity of the construction area and to preventing loss of use unit property

    Timely passage through supervisors where there is a risk of loss to or impact on the construction of the project

    Reporting to the contractor. Losses due to blind construction by the bidder or inadequate consideration of external environmental factors

     
    ReportFavorite 0Tip 0Comment 0
    >Related Comments
    No comments yet, be the first to comment
    >SimilarEncyclopedia
    Featured Images
    RecommendedEncyclopedia