Air conditioning maintenance programme 73164 - page 1
Air-conditioning maintenance programme
Programme book
April 2018
Air conditioning maintenance programme 73164 - page 1
Ac programme 73164 - page 2
I. Project overview
Project name: air conditioner maintenance
Project unit: company
Engineering scale: daily fluorinated cleaning and maintenance of 303 air conditioners, two central air conditioner hosts
Pipelines, etc., 2 repairs and maintenance, central air-conditioning mainframe oil replacement, soft water tanks, pumps
Replacement of electric axle bearings, replacement of indoor air conditioning.
Transport, transport: road transport
Ii. General segment
1 general provisions
1. 1 this regulatory document proposes technologies for air conditioning maintenance, etc
Request.
1. 2 this norm sets minimum requirements and does not provide for all technical details, nor
The provisions on standards and norms are not fully quoted and the supply side should provide for compliance with these norms and industrial standards
Quality products.
1. 3 contractors must be registered in the people's republic of china and qualified for construction work iii
Independent legal person of an enterprise of grade and above. ... The tenderer shall accompany the tender in providing the required proof of qualification man
Documentation of shipments . 5.
Ac programme 73164 - page 2
Air conditioning maintenance programme 73164 - page 3

1. 4 if the bidder does not object to the provisions of this norm in writing, it expresses its vote
The equipment provided by the subject fully meets the requirements of this norms, and where it is inconsistent with the requirements of this norms,
Each item must be listed in the “project unit technical discrepancy table”
In the table of technical discrepancies for project units, it is stated that "no difference,o
1. 5 the criteria used in this instruction are higher if inconsistent with the standards implemented by the bidders
Commencing.
1. 6 this instruction will be annexed to the order contract and will have the same legal effect as the contract ..
Failure to do so is determined by agreement between the parties to the contract during the negotiation of the contract.
1. 7 supply-side responsibilities: the terms of reference will include, but are not limited to:
1. 7. 1 provide all equipment and design instructions and manufacturing specifications in the tender.
1. 7. 2 provision of instructions for installation and use of equipment.
1. 7. 3 criteria for testing and testing, including test reports and test data ...
1. 7. 4 provision of drawings, a list of the manufacturing and quality assurance processes and other requirements of the tender
Information.
1. 7. 5 provision of relevant information for equipment management and operation.
1. 7. 6 the equipment provided shall be shipped to the specified destination and shall be responsible for on-site installation and commissioning ...
Air conditioning maintenance programme 73164 - page 3
Ac maintenance programme 73164 - page 4
1. 7. 7 if there is an apparent conflict between standards, norms and the provisions of this norm, the supplier shall manufacture
Prior to the equipment, the conflict and resolution are communicated in writing and confirmed by the required party only in
Equipment manufacturing.
1. 7. 8 supply side when replacing guidelines, standards, protocols or modifying technical data for equipment
The duty to accept the choice of the demand side.
General technical requirements
2. 1 quoting criteria
All spare parts, assembly components required for the project, including all attachments and accessories obtained by the construction party from third parties

Equipment, etc., other than the technical parameters and requirements specified in this instruction, shall follow the latest version
Standard dl for the electricity sector, national standards gb and iec and international system of units (isi)
Minimum requirements for equipment. The construction party must provide the tenderer with its own standards or specifications
Photocopies in chinese may only be adopted with consent, but not less than the relevant provisions of dl, gb and iec.
2. 2 maintenance requirements
1. The contractor is responsible for the completion of all major repairs.
2. Spare parts provided by the major repair contractor: see list of works.
3. The contractor undertakes to complete the construction within one month of the signing of the contract.
Iii. Equipment, materials
Material equipment to be provided by bidders:
Ac maintenance programme 73164 - page 4
Ac programme 73164 - page 5
Quota
Number of engineering project units
Numbering
Central air-conditioning mainframe switch
1kg130
Two hundred electromagnetic valves four
3 soft water tank 1
4 pumps for re-axis water cover 2
5 water pumps to replace kw15
6. Replacement of 10 indoor air conditioners
7 ac plus fluorine pressure 150
8 air-conditioning cleaning agent kg300
List of works:
1. Budget for volume of work as detailed in the list of volume of work.

2. The unit price or amount stated in the schedule for the volume list shall include the labour requirement, the construction unit
Fees for the use of ordnance, materials, other miscellaneous charges, quality checks, installation costs, repair of defects, insurance,
And the risks, liabilities and obligations expressly or implied by the contract, as well as management fees, profits, etc.
3. The final volume of work is based on the actual quantity of work performed.
Construction requirements
1. Technical requirements
Ac programme 73164 - page 5
Ac programme 73164 - page 6
L all equipment materials must be purchased to the specifications and models required by a and to the requirements of a in
Line installation.
2 equipment purchased by maintenance units from other plants, with all quality issues to be addressed by the maintenance unit.
3 maintenance unit to establish quality of equipment design, material selection, processing, manufacturing and testing
Guarantee system and strict compliance with contract equipment throughout its manufacture ...
2. Work to be performed by bidders
1 receipt and custody of equipment and materials required for construction, secondary handling of site equipment and materials, installation
Loading and testing, system testing and debugging, cleaning of used materials, engineering files and transfer of information
Completion and warranty.
2 purchases of equipment for which the bidders are responsible should be carried out in a timely manner in accordance with the schedule and related procurements
Results are reported in a timely manner to the user unit, the supervisor, so that the user unit can cooperate in a timely manner, such as delays in the delivery of procurement
The subject should be fully responsible.
3 provisional facilities for bidders:
4 bid parties should maintain a high level of responsibility and ownership during construction preparation and construction
Pay attention to the protection of finished goods in the vicinity of the construction area and to preventing loss of use unit property
Timely passage through supervisors where there is a risk of loss to or impact on the construction of the project
Reporting to the contractor. Losses due to blind construction by the bidder or inadequate consideration of external environmental factors