Quality security of industrial estates is at stake for the survival of the manufacturing industry, in the immediate context of a massive expansion of “industrial upswings” to consolidate land use and increase industrial concentration。
However, recent interviews with journalists have revealed that an enterprise has loaned tens of millions of dollars to a factory custom-made by the manyang group, the head industrial park developer, which has been identified by the authorities as “dangerous houses”. Quality problems such as cracks on floors and beam concrete in beehive form have placed a serious safety hazard on “industrial upstairs”。
The floor is cracking
It's a beam of concrete
The loan invested more than $17 million to customize a plant, but was not expected to be a tofu project. This has left the owner of micro-enterprises in guangdong city of fushan watershed new materials ltd., the owner of chai tsai。
The manyang group, dubbed “the landland of the industrial estates of bainimarama”, has a market slogan “letting a business have a home, make it easier to run a factory”. In 2020, tsai tsai tsai arrived at the high ming mansion city, located in the city of fukuo, in the city of fuoshan, and made a $100,000 deposit for a single-door factory, with a total of five floors and a total building area of 6219 square metres, to be made available to the high ming wan city development company。
In 2023, the developer handed over more than 3. 6 million pieces of property to the head of state and loaned 13. 7 million yuan to the bank, bought the factory and issued the property certificates。
In june 2025, there were plans to renovate the new plant as a production workshop for new materials. It was not expected that the workers were cleaning up to cover up the huge amount of dust on the ground, and that a large number of cracks had been found on the floor above the second floor, as well as concrete beams。

“the overall acceptance of the estate was completed in 2023 and the developer was the head enterprise, and we did not question the quality of the plant.” chai-tai said that the plant was still in a hairy state, but that since the second floor and above, the cracks on the floor were visible, the local floors and steel were exposed and were badly rusty, some of which even broke loose。
"all kinds of cracks are so dense that they are scary." “most of the cracks are split along the beams, with dense cracks around the pillars and an extended development. If in use, under the load of several tons of machines, the consequences are unimaginable.”
More serious is the problem of the pillars. The woodhouse pointed to the first floor and told reporters that “the heavy pillars are not strong enough, and the concrete inside the pillars is a hive”. He also pointed at the base of the derelict roof fence and said: “there is hardly any good, and the slurry of the roof drops off as quickly as it is of waste”
“the plant has now been identified as in danger and the plant cannot be brought into production. I'm also carrying millions of loans from the bank, more than $100,000 a month。
Following unsuccessful communication consultations with wanyang, tsai tsai tsai reported the situation to the department of urban and rural construction and water management of housing in the highlight district of foshan city. On 10 october 2025, the authority issued a dispositary opinion stating that “the high ming man ocean creative city development company ltd. Was urged to immediately take the lead in organizing the construction units, design units and supervisory units of the 53 factories in the city of high ming wan to investigate and verify the quality of the works at the plant”。
Two institutions
They're all "unusual" dangerous rooms
What is the quality of the work done for 53 factories in high-mixed cities with cracks, steel strips and parts of concrete in their beehive? The two authorities have been tested to give the answer: they have seriously affected the overall security and are not using it properly。

For the first time, chai tsai found a third-party testing company with accreditation to build the design company ltd. In august 2025, compagnie design ltd. Issued a reliability and anti-shock assessment of the plant, which clearly concluded: “the building is rated at the d level for its overall safety and the 4th level for its reliability, i. E. `very non-compliant with the reliability requirements of current national standards, which have seriously affected the overall security and are not properly used'.”
Industry experts point out that the level of safety and reliability of buildings is four (d level), meaning that the house is in a dangerous state as a whole, that is, in the usual sense of the term。
The validation report states that locally drilled structural column concretes have hives and that local vertical steel bars are too small to meet regulatory requirements. The scaffolding of the sorghum is evident in parts of the first layer; there are a large number of cracks on the panels of the floors; cracks vary in length from 2 to 3 metres for the most part; and the surface of the local floors is visible and rusty。
The findings of the third party commissioned by foshan city watershed new materials ltd. Were rejected by foshan high mixture-wang city development ltd. Following consultations, the parties jointly commissioned a second house safety test at guangdong construction quality security station limited。
At the end of february this year, guangdong construction quality safety inspection company ltd. Issued an appraisal report, which essentially maintains the findings of the construction consensual design company ltd.: “in accordance with the standard for the validity of industrial buildings, the structure of the building is of d level and the reliability level of iv level”
The validation report states that a total of 21 plate steel protection layers with cracks were sampled for a total of 126 points, 78 were ineligible, with a 38 per cent pass rate。
In the relevant documents issued by the local housing authorities, journalists found that 53 factories in the town of visumi, which had serious engineering quality problems, had applied for joint acceptance on 6 january 2023, and that the local authorities had completed the receipt and inspection file on 11 january 2023, after being reviewed and processed。
In june 2024, march 2025, june 2025 and june 2025, the housing and urban and rural construction directorate of jiangsuyan city, the housing and urban construction directorate of jiangdong jiangmen city, the housing and urban and urban construction directorate of guangdong yunfou city, and the urban and rural construction directorate of guangdong city, respectively, reported problems in the quality of the works of the local manyang city building project, such as the three generations project in tsuruyama, the presence of individual concrete components such as hives, falcones, and the emergence of the first bands in the fifth pillar of the city (part one) of the cloud。

On related issues, vice-president dai gyeongbin of the manyang group told journalists that it had been determined that 53 of the buildings in the city of high mixture had been designed to be “irregularly used” and needed to be reinforced to be used, but not in a situation requiring total demolition, which was due to problems that had arisen during the construction process. We and the owners have agreed on a follow-up reinforcement programme。
Rapid expansion
"acetacin" adds to the engineering hazard
According to industry sources, the “low-cost +-scale” approach has matched the huge market demand for the upgrading of traditional manufacturing and the “upside industry”, but the rapid expansion has led to a failure to keep the management chain up, and the “a-b” phenomenon has further increased the risk of engineering quality。
The manyang group network of officials shows that the manyang group was founded in 1998 as a china-china national enterprise with a total industrial chain system for investment development, industrial recruitment, construction and park operation。
In the interior of the pearl triangle, the town of foshan, which is home to many people, has a total planned land of approximately 1100 acres, with a total investment of 9 billion yuan, in six stages of development, and is expected to accommodate 200 enterprises once it is built. By 2024, 39 plants had been completed and 56 enterprises had been introduced。
The main problem, analysed by the industry, is that the development of a self-building model for the aether convergence in mount fueyang, which is part of the business blocks of the man-yang gang, man-yang construction, man-yang wisdom operations, man-yang finance, etc., is likely to emerge from the construction and construction of the man-yang gang. Left-handed, right-handed, construction, etc. Did not compete in the market. As long as you can get the land, the money is for yourself.”
In the view of the industry, the development of a self-building model for the “aether conglomerate” has advantages in terms of cost control, coordination of progress and so on, but is prone to problems of “self-monitoring”. In the absence of effective checks and balances, the procurement of materials and construction standards may be reduced by internal conflicts of interest, while third-party supervisory units are often unable to function effectively because of a high degree of convergence of interests。