Model operational specifications for reheating pumps and recycle pumps: i. Standard 1. Operators of reheating pumps shall have basic operating principles and operating procedures. 2. The equipment shall be routinely inspected prior to operation to ensure that there are no malfunctions or anomalies, and any problems shall be reported and resolved immediately. 3. The start-up steps of the recharge pump are as follows: a. Open the pump entering valve, ensure the flow of the recharge pipe and prevent air from entering the pump body. B. Confirms that the pumps and the electric cabinets are connected and checks whether the pumps are connected properly. C. Press the start button to activate the recharge pump. At the same time, the operation of the pumps is monitored to ensure that the export pressure remains within the predefined range. D. When the operation is stopped, press the stop button and then close the water valve. 4. Conduct periodic inspections of the operational status of the recharge pumps and of the electrical equipment, and find that anomalies should be dealt with promptly to ensure the safe and stable operation of the equipment. 5. Special attention needs to be paid to the operation of recharge pumps in extreme weather or other exceptional circumstances and, where necessary, appropriate measures to ensure their normal operation. Ii. Rotation station cycle pump operating instruction 1. Operators should be familiar with the working principles and operating procedures of the cycle pump. 2. Prior to the start-up of the cycle pump, the equipment shall be confirmed to be functional and, in case of failure or anomaly, shall be reported and resolved immediately. 3. The start-up of the cycle pump is as follows: a. Ensure that the power source of the cycle pump is connected and check that the power line of the pump is not unusual. B. Press the start button, activate the cycle pump and observe its operational status to ensure that the export pressure is within the set range. C. When the operation is stopped, press the stop button and then cut the power of the cycle pump. 4. Periodically inspect the operation of the cycle pumps and the working state of electrical equipment and find extraordinary and timely processing to ensure the safe and reliable operation of the equipment. 5. In case of severe weather or other exceptional circumstances, special attention should be paid to the operation of the circulation pump and, if necessary, to the timely implementation of appropriate measures to ensure its proper operation. Key points and attention: 1. Operators must be familiar with the working principles and operating processes of refilling and recycling pumps. Pre-operational equipment inspections are essential and any malfunctions or anomalies should be reported and resolved immediately. 3. At the start-up of the pump, it shall be carried out in strict accordance with operational specifications to ensure that the operation is correct. 4. Periodic inspection of the operation of the pumps and the state of electrical equipment and timely handling of anomalies to ensure the safe and stable operation of the equipment. 5. Special attention needs to be paid to the operation of pumps in the face of exceptional conditions, particularly severe weather conditions, and appropriate measures should be taken to ensure that the pumps work properly. This is a simplified version of the oop template, which can be expanded and revised to fit the specific word number protocol according to actual needs. Please note that specific protocols should be prepared on the basis of actual equipment and operational requirements and be approved and approved by professionals. The main components of the reheating station pump, the recycle pump operation protocol, van (ii) i, the introduction to the reheating station are the refilling pump and the recycle pump, which have a decisive impact on maintaining the proper operation of the heating system. In order to ensure the safe and stable operation of both types of equipment, this protocol has been developed to clarify operational steps and safety guidelines. Operating procedure (i) pump operation step 1. Open the pump room door to confirm that the interior lighting equipment is functional. 2. Check whether the recharge pump power switch is closed. 3. Activate the recharge pump by pressing the start button, while observing whether the operational light is on to confirm that the equipment has been activated. 4. Periodically inspect the operation of the recharge pumps, including vibrations and sound, and detect anomalies that should be stopped immediately and reported to superiors. 5. Regular monitoring of environmental parameters such as temperature and humidity in the pump room during the operation of the recharge pump to ensure an appropriate operating environment. When the recharge pump is to be stopped, press the stop button and finish the operation. 7. Confirms that the recharge pump operation light has been extinguished and that the equipment has been completely disabled. Close the pump room door. (ii) cycle pump operating step 1. Open the recycle pump door to ensure proper lighting in the room. 2. Check whether the cycle pump power switch is closed. 3. Activate the cycle pump by pressing the start button while observing whether the running light is on to confirm that the equipment has been activated. 4. Periodically check the operation of the cycle pumps, including vibrations and sound, and detect anomalies that should be stopped immediately and reported to superiors. 5. Regular monitoring of environmental parameters such as temperature and humidity in the pump room during the operation of the cycle pump to ensure an appropriate operating environment. 6. When the cycle pump needs to be stopped, press the stop button to finish the operation. 7. Confirms that the circulation pump operation light has been extinguished and that the equipment has been completely disabled. Close the recycle pump door. Iii. Safety precautions (i) pre-operational safety of recharge pumps: 1. Ensure that recharge pumps are shut down and take appropriate safety precautions to prevent risks arising from mishandling. 2. During the operation, the operation of the recharge pump shall be closely monitored to detect and address anomalies in a timely manner. 3. During the operation, non-operators shall not enter the pump room to avoid accidents. Upon completion of the operation, it was confirmed that the recharge pump had ceased operation and that the pump room door had been closed. (ii) the safety of the operation of the cycle pump is required to ensure that the power source of the cycle pump is shut down prior to operation and that appropriate safety precautions are taken to prevent risks arising from mishandling. 2. During the operation, the operation of the cycle pump shall be closely monitored to detect and address anomalies in a timely manner. 3. During the operation, non-operators shall not enter the cycle pump room to avoid accidents. 4. At the end of the operation, it was confirmed that the circulation pump had ceased operation and that the pump room door had been closed. It is concluded that the filling and recycling pumps play a key role in the heat exchange stations and are essential for the proper operation of heating systems. The proper operation and management of both types of equipment, in strict compliance with this protocol, ensures the safety of the equipment and maintains the stable operation of the heating system. We should keep an eye on the state of operation of the equipment and conduct regular maintenance to improve its efficiency and extend its useful life。