  • Project name of the project for the remediation and retrofitting of waste gas in the paint-painting

       2026-01-31 NetworkingName1420
    Key Point:Construction/protocol answer documents for the beijing aircraft maintenance engineering co. Ltd., chengdu sub-company 203 waste gas refurbishment and renovation project (project name)To potential bidders:The following responses are provided to the questions raised by bidders in the tender for the beijing (slightly) chengdu sub-company 203 waste gas retardation and retrofitation project (project name):1 chapter ii bidders are required to know the

    Construction/protocol answer documents for the beijing aircraft maintenance engineering co. Ltd., chengdu sub-company 203 waste gas refurbishment and renovation project (project name)

    To potential bidders:

    The following responses are provided to the questions raised by bidders in the tender for the “beijing (slightly) chengdu sub-company 203 waste gas retardation and retrofitation project (project name)”:

    1 chapter ii bidders are required to know the list of additions to the previous schedule. 14 bidders are required to download and stamp the full business credit information bulletin (abbreviated) from the date of receipt of the solicitation documents to the tender deadline, with no fewer than 20 participants in the previous year's social security 5 insurance. Question: after consultation with shenzhen social security, social security-related data will not be uniformly publicized until 30 june, and 2024 now shows zero. Could the previous year's data be supplemented by data from 2023 or (slightly) documentation of the number of social security recipients

    Response: yes. The term “previous year” in the solicitation documents “no less than 20 participants in the previous year's vms” refers to 2023 or 2024。

    Sichuan aircraft maintenance engineering ltd

    2 chapter ii bidders are required to know that the stamping requirements of 3. 7. 3 in the preceding schedule are: (1) the electronic stamp stamping of the legal representative shall be applied to all places where the stamping is required in the electronic tender documents. Where a legal representative is required to be stamped by another person, including a delegated agent, his bid will be rejected. Question: chapter viii. Legal representatives: (signatures), representatives: (signatures) and legal representatives' electronic seals may be printed in the tender document format “ii, power of attorney”

    Answer: no. The project may be tendered by a legal representative without having to commission a tender. In the event that an agent is required to submit the tender, the agent shall also perform the corresponding electronic seal and place the electronic seal at the appropriate place in the tender document。

    Candidate: beijing (slightly) chengdu

    Tender agent: sichuan huatung construction (slightly)

    13 march 2025

    Sichuan aircraft maintenance engineering ltd

    Construction/protocol answer documents for the beijing aircraft maintenance engineering co. Ltd., chengdu sub-company 203 waste gas refurbishment and renovation project (project name)

    To potential bidders:

    The following responses are provided to the questions raised by bidders in the tender for the “beijing (slightly) chengdu sub-company 203 waste gas retardation and retrofitation project (project name)”:

    1 chapter ii bidders are required to know the list of additions to the previous schedule. 14 bidders are required to download and stamp the full business credit information bulletin (abbreviated) from the date of receipt of the solicitation documents to the tender deadline, with no fewer than 20 participants in the previous year's social security 5 insurance. Question: after consultation with shenzhen social security, social security-related data will not be uniformly publicized until 30 june, and 2024 now shows zero. Could the previous year's data be supplemented by data from 2023 or (slightly) documentation of the number of social security recipients

    Response: yes. The term “previous year” in the solicitation documents “no less than 20 participants in the previous year's vms” refers to 2023 or 2024。

    2 chapter ii bidders are required to know that the stamping requirements of 3. 7. 3 in the preceding schedule are: (1) the electronic stamp stamping of the legal representative shall be applied to all places where the stamping is required in the electronic tender documents. Where a legal representative is required to be stamped by another person, including a delegated agent, his bid will be rejected. Question: chapter viii. Legal representatives: (signatures), representatives: (signatures) and legal representatives' electronic seals may be printed in the tender document format “ii, power of attorney”

    Sichuan aircraft maintenance engineering ltd

    Answer: no. The project may be tendered by a legal representative without having to commission a tender. In the event that an agent is required to submit the tender, the agent shall also perform the corresponding electronic seal and place the electronic seal at the appropriate place in the tender document。

    Candidate: beijing (slightly) chengdu

    Tender agent: sichuan huatung construction (slightly)