    Key Point:PmpExamples of project experience2019At the beginning of the year, i participated as project manager in a digital transformation project in a manufacturing enterprise。The objective of the project is to provide access to core models of finance, procurement, inventory, production and human resourcesBlock, establishment of a unified enterprise resource management platform, data access, process standardization and determinationPlan speed. Tota

    Pmp

    Examples of project experience

    2019

    At the beginning of the year, i participated as project manager in a digital transformation project in a manufacturing enterprise。

    The objective of the project is to provide access to core models of finance, procurement, inventory, production and human resources

    Block, establishment of a unified enterprise resource management platform, data access, process standardization and determination

    Plan speed. Total project investment is about $50 million

    12

    Months, all over the country

    Molecular companies and external suppliers. The challenges and opportunities that i've been facing have been paralleled throughout my life cycle

    Used in

    Pmbok

    Pmp project empirical description model

    Knowledge areas and tools to facilitate projects from project formulation to completion

    Close the ring。

    I. Systemic work on project formulation and start-up

    During the start-up phase, i first participated in the preparation of the project charter, identifying business needs, projects

    Objectives, key success factors, border conditions and initial resource budget. To ensure high-level support

    Earth, i'm united

    Pmo

    The team created a profit map that will

    Cost savings, stock rotation, extraction

    Synergy, productivity improvement, data governance

    When the multiple profit lines are structured into measurable indicators

    As a benchmark for follow-up assessment and acceptance. An initial risk register was subsequently established, listing potential

    Pmp project empirical description model

    The basic framework for change control is defined in terms of risks, impact levels and initial response strategies。

    When i formed the working group, i selected the core team that crossed the line:

    It/

    Application implementation, finance

    Cost

    Management, procurement and supply chain, production site, human resources, legal compliance, etc., to ensure each

    Critical areas can be involved in demand clarification and decision-making. After signing the minutes of the project launch, we were..

    It enters the planning phase。

    Ii. System design and planning for the planning phase

    In the planning phase, i led the team to complete the scopes

    Wbs

    Progress plan, achievements

    Pmp project empirical description model

    This plan, quality management plan, risk management plan, communications plan and procurement management plan, etc

    Core document. In terms of scope, we break down the structure through work

    Large system on line

    Disassemble as

    Several enforceable sub-packs, e. G

    Erp

    Core modules, data governance, interface interface, training and

    Upline support, etc., to ensure that the delivery, acceptance and inspection standards and responsible persons for each sub-contract are clear and clear。

    In terms of progress, milestones were adopted and key path analyses were combined, and set

    12

    Step of the month

     